Cheniere Partners Raises 2026 Distribution Floor to $3.30
The Sabine Pass owner lifted the low end of its full-year distribution range to $3.30 a unit and declared a $0.890 quarterly payout after third-quarter net income of $639 million.
Cheniere Energy Partners, L.P. (CQP) tightened its full-year 2026 distribution guidance to $3.30–$3.40 per common unit from $3.10–$3.40, keeping the $3.10 base distribution intact.
The Sabine Pass owner declared a cash distribution of $0.890 per common unit for the third quarter, comprising a $0.775 base and a $0.115 variable amount, payable November 13 to unitholders of record as of November 3. That variable portion was larger than the $0.045 variable paid with the second-quarter distribution of $0.820 and the $0.015 variable paid with the first-quarter distribution of $0.790.
For the three months ended September 30, 2026, the company generated revenue of $2.574 billion, up 7% from $2.404 billion a year earlier, after a 5% year-over-year increase in the second quarter. Net income was $639 million, or $1.01 a unit, up 26% from $506 million, or $0.80 a unit, a year earlier. Adjusted EBITDA was $954 million, up 8% from $885 million.
The company said the net-income increase was primarily driven by higher total margins on LNG delivered, from higher volumes recognized in income and higher margins per MMBtu. LNG revenues were $1.956 billion, versus $1.837 billion a year earlier; affiliate LNG revenues were $567 million. Operating and maintenance expense was $236 million.
LNG cargoes exported were 104, unchanged from 104 a year earlier. Volumes loaded and recognized were 378 TBtu, up 1% from 374 TBtu. Cash and cash equivalents were $569 million as of September 30, 2026, versus $182 million at year-end 2025; total available liquidity was $2.477 billion, including $1.873 billion of available commitments under two revolving credit facilities.
In October, Sabine Pass Liquefaction entered a long-term LNG sale and purchase agreement with QatarEnergy to supply up to 2 million tonnes per annum on a free-on-board basis beginning in the early 2030s through 2054, with 1 mtpa subject to, among other things, a positive final investment decision on the first phase of the SPL Expansion Project.
In September, the Federal Energy Regulatory Commission issued the final environmental impact statement for that expansion, and Cheniere Partners obtained term-loan commitments to finance construction costs of the first phase not expected to be funded with available cash. The loan is being sized to finance approximately 50% of the total estimated project costs of the first phase. Closing and funding are subject to customary conditions, including a positive FID. The first phase includes Train 7 and a boil-off gas re-liquefaction unit, with expected capacity of over 6 mtpa including estimated debottlenecking. FERC siting and Department of Energy export applications remain pending.
The company said the variable distribution takes into consideration, among other things, amounts reserved for annual debt repayment and capital allocation goals, anticipated capital expenditures to be funded with cash, and cash reserves.